From design to first cargo, one contractor.
The largest-capacity FLNG EPCIC project ever undertaken by a Chinese contractor — a standardized design recognized by a global major, delivered end to end.
The project
- Client
- Eni SpA
- Wison scope
- EPCIC
- Location
- Pointe-Noire, Republic of the Congo
- First LNG cargo
- 2026Feb
The asset
- Annual capacity
- 2.4MTPA
- Length overall
- 376m
- Offshore commissioning to first cargo
- 4months
- Liquefaction
- −162°C
Milestones
Tested in the yard. Proven offshore.
- Yard
Yard gas trial
Gas trial in our own yard before sail-away, to leave risk behind on shore.
- 2025
Sail-away
Towed from our yard to the Republic of the Congo.
- 22 Jan 2026
First LNG
First LNG produced offshore Pointe-Noire.
- 7 Feb 2026
First cargo
First LNG cargo offloaded side by side to a carrier.
- Jun 2026
Performance test
Complete performance test of the plant.